Milestones

Milestone number Milestone name Related work package(s) Due date (in month) Means of verification
M1 Project kick-off meeting held all M3 Meeting held
M2 Data Committee established 5 M3 First meeting held
M3 Stakeholder group recruited 3 M6 First meeting of the full group held
M4 New instrumentation installed in Belgrade and data flow established 1,2 M8 First data available
M5 Training for field campaigns completed 1 M10 Event held
M6 First field campaign started 2 M12 Progress report M12
M7 Chemical and biological characterization of collected samples started 2 M18 Data available
M8 Data archive compliant with data management plan established 2,5 M18 Data archive available for data inputs
M9 At least two ICLs held 1,2 M24 Results available
M10 Training for PMF completed 1 M24 One scientist trained
M11 Chemical and biological characterization of samples completed 2, 3 M26 Data available for analysis